New gas turbines UGT 45000 and UGT 60000 are under development stage to be used for power generations.
GTE-45 (rated power 45 MW) and GTE-60 (rated power 60 MW) are focused on new and retrofitted co-generation/ combine-cycle power plants.
GTE-60 well match for retrofit the existing boilers of steam capasity 500-600 t/h via build-in of gas-turbine unit and conversion steam-turbine cycle into combined cycle.
Cycle |
Unit type |
Power, MW |
Efficiency |
Fuel consumption |
|
|
|
electr. |
% |
BTU, kW·h |
gas (nm3/h) Hu=8555 kcal/nm3 |
Simple |
UGT 45000 |
45.0 |
34.4 |
9920 |
13150 |
Combined |
UGT 45000CC1 |
66.1 |
50.8 |
6720 |
13080 |
|
UGT 45000CC2 |
132.2 |
50.8 |
6720 |
26160 |
Simple |
UGT 60000 |
60.0 |
37.0 |
9220 |
16300 |
Combined |
UGT 60000CC1 |
83.8 |
52.1 |
6550 |
16150 |
|
UGT 60000CC2 |
167.6 |
52.1 |
6550 |
32300 |